Reversals and backdated completions on the four milestones that move money wait here until a person releases them. Nothing on this page has been sent to Monday or HubSpot.
3 waiting on a person
| Milestone | Job | Change | Filed | Status | Actions | |
|---|---|---|---|---|---|---|
| Slab DownRQ-118 · Construction | 25211A. Davoile and C. Alex | Status: from Completed to In ProgressBuilder’s date: from 22 Jun 2026 to — “Forma says the slab failed its engineer's inspection and is being re-poured.” | S. Hart · Today, 08:41Phone call | Waiting | ||
| Plate HeightRQ-117 · Construction | 25478S. and P. Nakamura | Builder’s date: from 12 Jun 2026 to 05 Jun 2026 “Move Homes' weekly report has the frame inspection on 5 June, not 12 June.” | A. Carter · Today, 07:58Vendor portal | Waiting | ||
| Settlement ConfirmationRQ-116 · Pre-construction | 23912J. and A. O'Connell | Status: from Completed to Not StartedBuilder’s date: from 28 Jul 2026 to — “The developer re-booked land settlement; 28 July did not go ahead.” | S. Hart · Yesterday, 16:20Broker email | Waiting |